TUNNEL BASICS AND CLASSIFICATION & SUPPORTING SYSYTEM

Tunnels: 
A tunnel is an underground or underwater passageway, enclosed except for entrance and exit, commonly at each end.
A tunnel may be for foot or vehicular road traffic, for rail traffic, or for a canal. The central portions of a rapid transit network are usually in tunnel. Some tunnels to supply water for consumption or for hydroelectric stations or are sewers. Utility tunnels are used for routing steam, chilled water, electrical power or telecommunication cables, as well as connecting buildings for convenient passage of people and equipment.

Tunnels are generally grouped in four broad categories, depending on the material through which they pass: soft ground, consisting of soil and very weak rock; hard rock; soft rock, such as shale, chalk, and friable sandstone; and subaqueous.

While these four broad types of ground condition require very different methods of excavation and ground support, nearly all tunneling operations nevertheless involve certain basic procedures: investigation, excavation and materials transport, ground support, and environmental control. Similarly, tunnels for mining and for civil-engineering projects share the basic procedures but differ greatly in the design approach toward permanence, owing to their differing purposes. Many mining tunnels have been planned only for minimum-cost temporary use during ore extraction, although the growing desire of surface owners for legal protection against subsequent tunnel collapse may cause this to change.


By contrast, most civil engineering or public-works tunnels involve continued human occupancy plus full protection of adjacent owners and are much more conservatively designed for permanent safety. In all tunnels, geologic conditions play the dominant role in governing the acceptability of construction methods and the practicality of different designs.



7.2GEOLOGICAL CLONTROl
Thorough geologic analysis is essential in order to assess the relative risks of different locations and to reduce the uncertainties of ground and water conditions at the location chosen. In addition to soil and rock types, key factors include the initial defects controlling behaviour of the rock mass; size of rock block between joints; weak beds and zones, including faults, shear zones, and altered areas weakened by weathering or thermal action; groundwater, including flow pattern and pressure; plus several special hazards, such as heat, gas, and earthquake risk. For mountain regions the large cost and long time required for deep borings generally limit their number; but much can be learned from thorough aerial and surface surveys, plus well-logging and geophysical techniques developed in the oil industry. Often the problem is approached with flexibility toward changes in design and in construction methods and with continuous exploration ahead of the tunnel face, done in older tunnels by mining a pilot bore ahead and now by drilling. Japanese engineers have pioneered methods for prelocating troublesome rock and water conditions.
The dominant factor in all phases of the tunneling system is the extent of support needed to hold the surrounding ground safely. Engineers must consider the type of support, its strength, and how soon it must be installed after excavation. The key factor in timing support installation is so-called stand-up time—i.e., how long the ground will safely stand by itself at the heading, thus providing a period for installing supports. In soft grounds  can vary from seconds in such soils as loose sand up to hours in such ground as cohesive clay and even drops to zero in flowing ground below the water table, where inward seepage moves loose sand into the tunnel. Stand-up time in rock may vary from minutes in raveling ground (closely fractured rock where pieces gradually loosen and fall) up to days in moderately jointed rock (joint spacing in feet) and may even be measured in centuries in nearly intact rock, where the rock-block size (between joints) equals or exceeds size of the tunnel opening, thus requiring no support.


7.3ENVIRONMENTAL CONTROL
In all but the shortest tunnels, control of the environment is essential to provide safe working conditions. Ventilation is vital, both to provide fresh air and to remove explosive gases such as methane and noxious gases, including blast fumes. While the problem is reduced by using diesel engines with exhaust scrubbers and by selecting only low-fume explosives for underground use, long tunnels involve a major ventilating plant that employs a forced draft through lightweight pipes up to three feet in diameter and with booster fans at intervals. In smaller tunnels, the fans are frequently reversible, exhausting fumes immediately after blasting, then reversing to supply fresh air to the heading where the work is now concentrated.


7.4ROCK SUPPORT
Most common loading on the support of a tunnel in hard rock is due to the weight of loosened rock below the ground arch, where designers rely particularly on experience with Alpine tunnels as evaluated by two Austrians, Karl V. Terzaghi, the founder of soil mechanics, and Josef Stini, a pioneer in engineering geology. The support load is greatly increased by factors weakening the rock mass, particularly blasting damage. Furthermore, if a delay in placing support allows the zone of rock loosening to propagate upward (i.e., rock falls from the tunnel roof), the rock-mass strength is reduced, and the ground arch is raised. Obviously, the loosened rock load can be greatly altered by a change in joint inclination (orientation of rock fractures) or by the presence of one or more of the rock defects previously mentioned. Less frequent but more severe is the case of high geostress, which in hard, brittle rock may result in dangerous rock bursts (explosive spalling off from the tunnel side) or in a more plastic rock mass may exhibit a slow squeezing into the tunnel. In extreme cases, squeezing ground has been handled by allowing the rock to yield while keeping the process under control, then remining and resetting initial support several times, plus deferring concrete lining until the ground arch becomes stabilized.

7.5ROCK MASS CHARACTERIZATION
Tunnel engineers generally classify rocks on the basis of resistance to deformation (strength), amount of weathering, and general resistance to weathering. (Parker, 1996) These last two are not the same, although they may seem so at first glance. A rock may be very resistant to weathering, but may have also have been subjected to a very long period of time, which may result in significant weathering. In general, the strength and resistance to weathering of a rock is derived from the class of rock. Igneous and metamorphic rocks, in general, are more resistant to deformation and weathering than sedimentary rocks.
Class
Descriptor
Unconfined Stress
Range (psi)
Unconfined Stress
Range (MPa)
R0
Extremely soft
20-100
0.2-0.7
R1
Very low strength
100-1000
0.7-7
R2
Low strength
1000-4000
7-28
R3
Moderate strength
4000-8000
28-55
R4
Medium high strength
8000-16,000
55-110
R5
High strength
16,000-32,000
110-220
R6
Very high strength
>32,000
>220














7.6 Importance of Geology  in Planning of Tunnels

Ø  Geology dominates the feasibility, behavior and cost of tunnel.
Ø  To know type of material  soil and rock type.
Ø  Good geological planning allows Engineer to plan for various uncertainty risk right from the beginning, decreasing the likely hood of an unexpected delay in the middle of project.
Ø  Weak beds & Zones including faults and shear zones.
Ø  Ground water , including flow pattern  and pressure.
Ø  Helps in selection of alignment and construction method.








 7.7 Rock Mass Rating

      Determined on basis of 5 parameters :
Ø  U.C.S.(Uniaxial Comp. Strength).
Ø  R.Q.D.(Rock Quality Design).
                                        RQD = solid core having length more than
                                                 �1cm/total length of drill.                                
Ø  Joint Parameter.
Ø  Weathering Condition.
Ø  Water  Condition.
Ø  R.M.R.=U.C.Q.+R.Q.D.+J.P.+W.C.+Water Cond.


 7.8 RMR & Rock Classification



RMR
ROCK QUALITY
0 – 20
Very Poor
21 – 40
Poor
41 – 60
Fair
61 – 80
Good
81- 100
Very Good










7.9Tunnel 5 Specifications (at CH:157+660) (PRACTICAL EXAMPLE)

Since the road exists in hilly terrain there are 5 tunnels along the newly aligned plan.I worked at Tunnel 5 which falls in Village Bhuwana of Distt Bilaspur, Himachal Pradesh & is 740metre long.


Ø  Location of Tunnel           : .......................
Ø  Chainage  CH                  : From  �157+66  to  �158+4m.
Ø  Length of tunnel              : 74m.
Ø  Finished Size                   : �1.59m x 7.58m.
Ø  Formation level

Portal 1      : 6�19.95m.
Portal 2      : 634.78m.


Ø  Shape of Tunnel                : Horseshoe.
Ø  Days of Completion           : 8 Days.
Ø  Mechanical Ventilation      : Apllied
Ø  Excavation Method            : Drill & Blast (NATM)
Ø  Type                                 : Single tube,two lane,bi-directional traffc tunnel.
  




7.9.1Cross Section of Tunnel


7.9.2 Geotechnical Profile of Tunnel









7.10 SUPPORT SYSTEM CLASSIFICATION

By studying the RMR value of the rock masses present at Tunnel 5 Portal 2, 7 support systems were defined:

        i.            A1
      ii.            A2
    iii.            B1
    iv.            B2
      v.            C1
    vi.            C2
  vii.            L

Support systems A1, A2, B1, B2 are used to support the strong rock mass, while the C1 C2 and l classes are used to provide support for the loose rock mass.

 


7.11PRE-EXISTING STRUCTURE

Ø  Portal segmented into 4 benches
Ø  Height of top three bench-7m
Ø  Height of bottom bench-12m
Ø  Slope-1:5 per bench
Ø  Stabilising method
·         Shotcrete lining
·         Rock bolting
·         Wire mesh



Ø  Shotcrete Details
·         M25 Grade
·         Min quantity of cement-400kg/m3
·         Aggregate size-10mm
·         Thickness-0.15m


Ø  Wire mesh
·         Fy-415N/m2
·         Dimension-150mmx150mmx6mm    

Ø  Rock Bolts
·         32mm dia
·         Fully grouted
                  Grouting mortar M20 grade with water cement ratio:0.3
7.12Cycle Process for Excavation of  Tunnel
A.For Good Rock Condition
 
1. Profile Marking.
2. Drilling.
3. Blasting.
4. Defuming.
5. Mucking.
6. Rock Support- Shotcrete/ Rock Bolt.

B.For Poor Rock Condition

1. Profile marking.
2. Drilling.
3. Blast.
4. Defuming.
5. Shotcrete.
6. Mucking.
7. Rock Support-Swellex Drill & Insert,Rock Bolt, Ribs, wiremesh, Shotcrete, lattice Girder.



  Profile Marking
  Surveyor marks the profile of drilling on face of Tunnel with the help of Total
  Station

    Drilling
Ø  Drilling Method is decided on type of geological conditions and necessary drill hole diameter.
Ø  Holes shall be either drilled by rotary method with water flush or pneumatic percussion method with air/water or any other type such that the disturbances to the adjoining rock is minimal.
Ø   Use of bentonite, rod grease or other lubricants is not allowed.




Blasting
Blasting Technique is considered as pre  specifications for controlling the complete rock surfaces.
 
Specifications
Atleast 50% of drill hole traces of each round must be visible in the final rock surface distributed uniformly after the scaling of all loose and shattered rock that is liable to fall  before or during rock reinforcement installation.
Specifications of Explosives used in  Tunnel.
Quantity in Box – 25 kg
Length (mm)
Dia. of   Explosive(mm)
Weight(gm)
300
25
125
300
32
196
300
40
390


Ø  Mass of explosive per hole (Kg) = Volume of hole length Charged x Explosive Density.

Ø  After Explosion, Powder Factor is calculated :

Ø  Powder Factor =    Explosive Used/  Muck Generated.
                             
Ø  Powder Factor should be as low as possible.



     Defuming
     After Blasting, Face is left idle for Defuming. Normally it takes time upto 60min. But with
     Exhaust fan it takes upto 30 min.


     Mucking
     Removal of the excavated matter is called mucking.Mucking is done after defuming using
     excavator and dumper. Normally it takes upto 3-4 hrs.


Wire  Mesh
Ø  Wire Mesh consists of welded wires in a fabric. Wire Mesh is installed in surface and underground excavation as reinforcement for shotcrete usually in combination with rock reinforcement.
Ø  Steel of minimum yield strength : 4�15N/mm2
Ø  Dimensions : �15´�15mm, with 6mm dia.

Shotcreting
 Shotcrete for tunnel supports may be used by itself as a thin skin type reinforcement or used in combinations with rock bolts, wire mesh and other  more conventional tunnel reinforcements. All loose rocks shall be sealed out and washed before applying shotcrete.  Shotcrete is forced into open joints, fissures, seams and irregularities in the      rock surface and in this way it serves the same binding function as mortar in a stone wall.
Shotcrete  hinders  water seepage from joints and seams in the rocks and thereby prevents piping of joint filling materials and air and water deterioration of  rock.

Type of  Shotcrete-
Ø  Dry Shotcrete
Ø  Wet Shotcrete

 Shotcrete Material  :
Ø  Minimum cement content: 400Kg/m3.
Ø  Maximum size of aggregates: 10mm.
Ø  Minimum strength (MPa) :   �1 day………�1�1
                                        7 days……..�17.5
   8 days……..5
Ø  FosRock was used as accelerator in Shotcrete.
Ø  Accelerator- 3% by weight of cement.




       Rock Bolt

        Types of Rock Bolt 
Ø  Expansion Shell Rock Bolt
Ø  Resin Grouted Rock Bolt
Ø  Rock Anchor Bolt
Ø  Grouted Anchor Bar

After completion of the drilling in rock the entire length of the hole shall be washed out with clean water.

Swellex Pipe
Ø  S75JR/SSteel quality 355MC.
Ø  It swells when high water pressure is applied from opening.
Ø  Diameter :32mm 




7.13 Rib Specification
It is used to support the rock along the circular portion inside the tunnel.
Ø  Hot rolled steel ISBH.
Ø  Installed at 1m Distance.
Ø  A=5.9cm2; M=4.Kg/m

5 Parts are joined togetherLength : L1 = 6.79m;  L2=L3 = 3.364m; L4=L5 = .33m.
With �16mm Dia, Bolt, Grade 4.6 ,Length = 3inch.Connected to steel pipes by welding.

7.14 Forepolling
The support class at portal 2 is L type hence forepolling is carried out before excavation to form umbrella cover. The forepolling was carried out by two techniques:

Ø  Dry drill
Ø  Wet drill

DRY DRILL
Dry Drill method is used drill has to be carried out in a loose rock soil mass. Dry drill is done by 




                                                      ROC machine.


WET DRILL is used to drill a hard rock mass. It is done by boomer machine.


        
   FOREPOLLING PATTERN
Ø  12m long drill of 104mm dia
Ø  MS pipes inserted in drilled hole and fully grouted
Ø  MS pipes having dia 76/89mm
Ø  Max yield load-1200KN
Ø  40mm dia rockbolt inserted in mild steel pipes
Ø  Grouted with M20 grade mortar having water cement raio-0.3
Ø  Inner crown forepolled at 3.5o and outer crown forepolled at 4.5o
Ø  An overlap of 3m provided for further forepolling inside the tunnel



 GROUTING THE FOREPOLL
 Forepoll is  grouted by M20 grade mortar having water cement ratio-0.28 and it is done by grout
 pump(20barr).



ROCK MOVEMENT ANALYSIS
The portal was equipped with several instruments to study various rock movements to analyse the safety and stand up time of tunnels. Major instruments used:
Ø  Optical survey targets
Ø  Extensometers
Ø  Inclinometer

OPTICAL SURVEY TARGETS
Optical survey targets are used to measure settlements if any due to the failure of support systems  provided.

                                           

 EXTENSOMETERS
Extensometers are used to measure the forward sliding of tunnels if any due to the relative movements of  rock masses.


Popular Posts